Picture this. Your estimator spends three meetings with a couple planning their kitchen. Somewhere in meeting two, over coffee at their dining table, he says sure, we can move the pot filler over the range. Small thing. He means to write it down.
Six weeks later, the plumber has roughed in, and the homeowner walks the site and asks where her pot filler is. Your PM has never heard of it. The plans don't show it. The estimator swears he mentioned it. Now you're choosing between eating the cost of moving rough plumbing or telling a client you're going back on a promise. Either way, you lose.
Your estimator sold one kitchen. Your PM built a different one. And it didn't happen because either of them is bad at their job. It happened because the handoff between them was a hallway conversation and a forwarded email.
Where the margin actually leaks
Most GCs have a solid sales process and a decent production process. What they don't have is a bridge between the two. Here's what usually falls through it:
Promises made in sales that never made it into the contract or the plans
Fuzzy allowances, so nobody knows the client is over budget until the invoice shows up
Selections still pending when the job mobilizes
The client's quirks and priorities, which live only in the estimator's head
Schedule commitments made to close the deal ("we'll be done before Thanksgiving")
Each one feels small. Together they add up to rework, change order fights, a client who stops trusting you, and margin that quietly disappears. On a $400K job, it doesn't take many "small things" to wipe out the profit.
The fix: one meeting, one page
Before any job mobilizes, hold a formal handoff meeting with your estimator, your PM, and whoever runs the office. Thirty to forty five minutes. Not optional, and not "when we have time."
Everyone works from one page that covers:
Scope and exclusions. What's in, and just as important, what's not.
Allowances and selections. Every allowance amount, and whether each selection is made, pending, or overdue.
Client promises and quirks. Anything said in a meeting that isn't in the plans, plus how this client likes to communicate.
Schedule commitments. Any date the client was given, in writing or out loud.
Budget by phase. So the PM knows where the money is before spending it.
Then two rules make it stick. First, the PM signs off on the page before the job starts. If it's not on the page, the PM didn't agree to it. Second, the client hears the exact same story at the preconstruction meeting. Walk them through the page so there are no surprises on either side.
That's it. No new software. One meeting and one sheet of paper that closes the gap where your margin has been leaking.
Steal my checklist
I turned this into a one-page handoff checklist you can print and use on your very next job.
Got a pot filler story of your own? Drop it in the comments. Want help building the fix? Book a call here.